Asphalt shortage halts opening of I-20 lane in Columbia

November 29, 2012 

— A shortage of asphalt delayed the re-opening of a lane along I-20 early Thursday, causing a headache for morning commuters in Northeast Richland.

Thad Brunson, district engineering administrator for the S.C. Department of Transportation, said the problem occurred on I-20 westbound, near Alpine Road.

Crews had taken up old asphalt along about a half-mile of the emergency lane, leaving a 10-inch drop-off at the edge of the road, Brunson said. About 2 a.m., the asphalt plant in Sumter providing replacement material broke down, leaving crews unable to re-open the lane by the required 6 a.m.

He said the traffic tie-up was “significant” for those heading into town, before the problem was resolved at 8:45 a.m., Brunson said.

“Any backup is not acceptable, but it was something that couldn’t be avoided,” Brunson said.

The S.C. DOT is widening 6.7 miles of I-20, from I-77 to Spears Creek Road. Lanes are being closed overnight to minimize the impact on drivers.

Work began in October and is expected to take two years.

-- Dawn Hinshaw

The State is pleased to provide this opportunity to share information, experiences and observations about what's in the news. Some of the comments may be reprinted elsewhere in the site or in the newspaper. We encourage lively, open debate on the issues of the day, and ask that you refrain from profanity, hate speech, personal comments and remarks that are off point. Thank you for taking the time to offer your thoughts.